Hackney’s failure to renew housing repair contract ‘has left contractors painting over mould’


Hackney Council failed to renew a major deal for housing repairs for over six years despite internal warnings over the decline of the borough’s social homes, the Local Democracy Reporting Service (LDRS) has learned.

To meet the various layers of compliance standards for its roughly 30,000 social homes, like all other local authorities in England Hackney Council is obliged to carry out repairs to its housing stock, of which there are two types: short-term or ‘reactive’ repairs and long-term capital works.

The council often outsources these jobs to third party contractors, and for efficiency it has relied on multi-year deals with preferred companies – known as ‘main contractor frameworks’.

Yet even though the council’s last framework expired in 2019, the local authority has repeatedly failed to secure a new one, piling pressure on its reactive repairs and leading to the council missing an entire structural repairs cycle, insiders have claimed.

In the nearly seven years since the contract expired, the council has twice been slapped with damning watchdog findings into its social housing. Together, the Regulator of Social Housing and the Housing Ombudsman found a litany of health and safety issues but also deep problems with how Hackney Council was handling soaring complaints around disrepair and maintenance.

Although the council has blamed the lingering impacts of the Covid-19 pandemic and a 2020 cyber attack which wiped vital housing data from its systems and hobbled its housing management system, council records and insider accounts suggest the lack of a contractor framework paralysed the council’s ability to carry out major structural works to its decaying stock.

The council triggered the procurement process for a new £180m contractor framework in October 2025 – its third attempt to do so. But this followed an earlier doomed effort to find a procurement shortcut the year prior, which the council pursued despite being warned of the legal consequences. The council has refused to disclose how much this failed procurement strategy cost.

Hackney Council has repeatedly declined to give its own account of why it had not secured a new framework, and why progress towards it was sluggish while numerous residents continued to languish in blocks like Fellows Court, whose occupants continue to plead with the council to address their “atrocious” conditions.

Interviews conducted by the LDRS with staff suggest the reason behind the council’s inability to replace the deal went beyond both the pandemic and cyber attack.

‘Like a rudderless oil tanker’

As early as June 2019, the council was warning that the high turnover of senior staff meant it did not have the internal expertise to replace the contractor agreement. Council reports state that many “key staff” had left as the council reabsorbed an arms-length management body, Hackney Homes, back into its teams.

Under procurement law, contract arrangements like these have strict lifespans to allow councils to change suppliers or adjust terms to reflect new guidance. The contract expired in November 2019 with no replacement in place, though the council was legally allowed to continue to use it for repairs and capital works until August 2020.

March 2020, the Covid-19 pandemic crisis hit with lockdown imposed, putting major capital works on hold. The council was then granted a one-year extension for the contract, ending in August 2021.