Two council contractors went bust in 2023 leaving over 200 affordable homes incomplete
Ealing Council is set to sell over 200 affordable homes after two of its housing partners collapsed during construction.
Across six stalled development sites approved for marketing – to be sold – are 208 affordable homes. A total of 230 half-built homes will be sold, 174 of which were marked for London Affordable Rent, 34 shared ownership homes and 22 for open market sale.
The largest site at Southall Market Car Park currently totals 125 homes, all of which were affordable. This is the only site where completing the existing standing structure may remain feasible – however it will still be put up for market sale.
The council previously explored restarting construction via a funding agreement with Mackenzie Homes, but terminated the agreement due to delivery and financial risks. The original builder – 4 Square Services – collapsed in mid-2023.
Dean Gardens in West Ealing was under construction by Henry Construction Projects, which went bust in 2023. The scheme featured 53 homes, including 31 which were affordable.
The council has determined that this site is not viable to complete. It is likely that the site will have to be demolished.
Chesterton and Evesham is another unfinished project likely to be demolished and sold by Ealing Council. Originally, the scheme planned for 25 Passivhaus homes – all affordable – as part of a £40 million contract awarded to Henry Construction.
Also included in the multi-million pound contract was the Wood End site in Northolt. All of these homes were scheduled to be affordable rentals – now, all are likely to be demolished.
The story is the same for other schemes including Shackleton Road and Norwood Road. Across both, 16 affordable homes were set to be built – now, all will likely have to be demolished.
Structural reviews determined that neither development was viable to retain due to individual structural defects and risks.
The decision taken by the council agrees to formally market the sites, with a final disposal plan set to return to Cabinet in the future, with all future bids recommended for approval. Councillor Louise Brett, Deputy Leader of the Council and Cabinet Member for Safe and Genuinely Affordable Homes, has also approved a £200,000 budget to fund marketing agents and other costs associated with the marketing.
The local authority considered council redevelopment of the sites which would have allowed the council to retain the homes and the rental income which would have been generated. However, council officers are of the opinion that “the most appropriate next step is to formally test the market for the disposal and development of the sites.”
Ealing Council says that “the purpose of the proposed marketing exercise is not simply to obtain land value offers, but to identify the most effective route to unlocking the development potential of the sites.”
The council argues it remains “committed to supporting housing delivery and regeneration objectives, and marketing will enable officers to explore whether alternative delivery approaches could achieve improved outcomes for residents whilst reducing risk to the council”.